Works to Main Road A7 Ballabeg 7 April 2011 The Department of Infrastructure announces that work will commence on Monday 11th April to resurface the carriageway between Duck Street and Friary Park and between Friary Park and Sycamore Cottage. The road will be closed between 9 am and 4:30 pm daily. We hope to finish the work before Easter on the 21st April but if the weather is poor the work may extend until Friday 29th April. This carriageway resurfacing will finish the road drainage improvement scheme carried out earlier in the year. The works are programmed to be carried out in four phases. During the first 2 phases the old road surface will be removed and the ironwork in the road reset to the height of the new road surface. During Phase 3 and 4 a new road surface to the new level will be laid, improving both the road surface and ensuring better drainage off the road. We will maintain pedestrian access to all properties for the duration of the work and school buses will have access through the site, unfortunately the normal public bus service will not be able to run through this area during the closed periods. Service 1 buses will divert via Shore Road between Ballakaighen Corner and Port Erin. The last buses to run via Ballafesson, Colby and Ballageg in the mornings will be: Port Erin departing at 8.37, Colby bridge at 8.50 Colby Bridge 8.45 Port Erin at 8.59 Emergency access through the site will be available at all times. The Department wishes to take this opportunity to apologise for any inconvenience caused by the closure and hopes the public will see major improvements to this area on completion of the scheme. More stories >>>
|