Recovery of Road Condition Following Severe Cold Weather Damage – Forward Plans 24 May 2011

As will have been widely observed, the Department has previously reported that the islands roads have suffered extreme damage following the last two uncommonly severe winters. We have already reported the immediate steps that have been taken.

Taking stock of the damage, it is clear that many of the roads are in an very fragile condition. Patching and pothole repair has been a vital short term measure as the Department’s first priority is to keep the roads safe. It is recognised however that such repairs do not last indefinitely and may be vulnerable to failure and also that many of the defects are due to the structural failure of the road and require more than patching or even full re-surfacing.

There are approximately 650 miles of road network on the island:

Strategic (Primary and secondary) - 250miles

Unclassified (Estate roads, rural roads and minor town roads) - 400miles

In the new financial year, based on load testing that shows underlying road condition, the Department has plans to use approximately £2.7M for a provisional programme of carriageway re-surfacing and re-construction on the islands strategic network:

  • A3 Lezayre Road, Ramsey – Reconstruction
  • A3 Main road, Foxdale- Reconstruction
  • A5 Castletown – Janet’s corner to Alexandra Bridge- Strengthening
  • A2 Glencrutchery Road, Douglas – Stabilise/Resurface
  • A5 Blackboards Bridge – Strengthening (abnormal load route)
  • Cooil Road, Vicarage Road to Mt Murray Back Road - Stabilise/Resurface
  • A1 Main Road, St John’s – Reconstruction
  • Victoria Rd, Governors Hill to Shoprite Rdt, Douglas

In addition Tynwald has approved an additional £1M for unclassified roads and footways and based on priorities established by visual inspection, the Department has established a provisional programme comprising:

  • Derby Road, Peel
  • Hailwood Avenue
  • Glen Darragh Road
  • Footways in Douglas Town which have the highest footfall and are in poor condition.

In addition the Department is progressing plans to re-construct the Promenade in Douglas and is also working through the Chief Ministers Regeneration Steering Group to deliver a range of work including highway improvements around the island.

Phil Gawne, Minister for Infrastructure said:

“Whilst this is a substantial and ongoing programme of planned basic road maintenance the Department remains concerned that the scale of the problem and the backlog of maintenance still requires further funding and attention. I will be working with senior officers to identify and seek further support given the scale of the issue that we face.”

The Department would like to remind people that defects can be reported via potholes@gov.im or by calling 686665.