Review of Maintenance Following Cold Weather Damage The Big Picture 8 July 2011 The Department has previously reported that Manx roads have suffered extreme damage following the last two uncommonly severe winters. Following the freezing weather, highway defect reporting rose to a peak of nearly 500 defect reports per month compared to more typical levels of around 100 per month. After a considerable recovery effort, we can report that the more immediate damage has been largely repaired with reporting levels now similar to those before the cold weather damage. However many of the roads remain in a very fragile condition. Patching and pothole repair has been a vital short term measure as the Departments first priority is to keep the roads safe. It is recognised that such repairs do not last indefinitely and may be vulnerable to failure and also that many of the surface defects are due to the structural failure of the road and require more than patching. The Department has a planned maintenance programmes of £3.7M in 2011/12 and has also chosen to re-prioritise its resources to focus on maintenance allowing it to try to protect the road asset by spending an additional £1M on surface dressing some of which has recently been used on the Mountain Rd. Surface dressing is one of the most cost effective ways of prolonging the life of a road. However, in considering the overall position, the Department has concluded that of the 650 miles of road network, approximately 200 miles of road requires reconstruction, re-surfacing or surface dressing and in order to undertake all of this work around £100M would be needed. To put this in context the re-construction of the entire network would cost approximately £1bn so the road asset is clearly one of Governments most valuable assets. Given the scale of the maintenance problem, and the difficult financial position facing Government at the moment, the Department will continue to try to use its highways budgets more effectively to try to deal with the problems identified. Minister Gawne said; We have already taken significant steps to re-prioritise expenditure towards maintenance and some additional funding has been forthcoming as previously announced, so we do have some significant investment agreed and projects planned. Clearly though, with the scale of the problem, made so much worse by the severe weather, I am asking people to perhaps limit their expectations on what can reasonably be delivered by the Department in these financially constrained times. The Department would like to thank members of the public for their phone calls and e-mails to report potholes and other defects and would ask them to continue to do so via potholes@gov.im or tel 686665. More stories >>> |